On the Job Ledger Report, where is the 'Progress Status' field coming from?

I see the percent complete is just static info pulled from the job master file, but my job is showing as "Completed" and I don't know why or where that is set or flagged.

TheWolf
08-14-2004, 10:56 AM
Progress status is based on percentage complete on the maintain jobs window. If it shows completed then the Job end date has been populated and you are past that date.